Village Services

Village Services

 

 

 

Public Works Projects

For additional information regarding any of the projects below, please contact the Public Works Department at 847-960-7500.

 

 

Projects Under Design & Awaiting Bids Description Est Start Est Finish % Comp Current Status
2008 Drainage Improvements Correct major drainage problems in various locations through out the original part of Lake in the Hills. Summer-08 Sept.-08 100% Bid opening was held on July 15 and the contract will be awarded at the Village Board Meeting on July 24.
Tower 3 Repainting This work consists of making minor repairs and priming and repainting the interior and exterior of the water tower. Sept.-08 Dec.-08 95% Bid openig was held on June 20 and the contract will be awarded at the Village Board Meeting on July 24.
Well 1, 2 & 5 Demolition This work consists of abandonig the wells and demolitioning the buildings at each site. Sept.-08 Dec.-08 95% Engineers are in the process of finalizing to scope of work.  Prep work is being done on the well houses this month before demolition.
Projects Currently Underway Description Est Start Est Finish % Comp Current Status
2008 MFT General Maintenance Program This Annual program continues the maintenance of existing Village streets. The project will consist of grinding existing asphalt surface and then placement of new asphalt, select concrete curb and drive aprons along the following roadways: Upper Blackhawk Dr, Patton Ave, Decatur Ave, Lee St, W. Oak St, Pershing Ave, Grant Ave, Clark Ave, Anderson Dr, Blackberry Ct, Spring Lake Ct, White Pine Ct, White Pine Circle, Astor Ct, Elderberry Ct, Mayberry Ct, Wisteria Ct and Spring Lake Dr.  Summer- 08 Sept.-08 0% The contract was awarded to Curran Contracting.  
2008 Water Main Improvements Program This annual program continues the maintenance and replacement of existing undersized and/or failing main. The project will consist of placing 8" watermain along the following roadways:  Hilltop Dr, Clayton Marsh, Washington St, Monroe St, Adams St, Jefferson St, Elm St and Spruce St. Spring-08 Nov.-08 0% The contract was awarded to Apollo Trenchless.  The pre-construction meeting was held June 4.  Letters were mailed to residents in the area of the project last week.  The contractor will be starting work in July.
Cheswick Park Installation of a new park at the corner of Albrecht Rd and Gladstone.  This park will consist of new playground equipment, pavillion, benches and tables, walking path and various plantings throughout the park. May-08 Jul-08 65% Contract was awarded to Copenhaver Construction.  The contractor is on-site and has started work.  All concrete work is complete.  The asphalt path is installed and the trees have been planted.  The contractor is waiting on the delivery of the playground equipment.
Recent Projects Completed Description Est Start Est Finish % Comp Current Status
Bordeaux Bike Path Removal This project consists of removing the bike path behind the homes along the southside of Bordeaux.     Apr-08 Apr-08 100% Complete

 

Lake in the Hills Village Hall
600 Harvest Gate
Lake in the Hills, IL 60156
847-960-7400

Hours: 8:30am - 5:00pm Monday - Friday

Finance Department has extended hours Thursdays until 7:30pm, providing limited services.

Disclaimer and Linkage Policy