Projects Under Design & Awaiting Bids |
Description |
Est Start |
Est Finish |
% Comp |
Current Status |
|
2008 Drainage Improvements |
Correct major drainage problems in various locations through out
the original part of Lake in the Hills. |
Summer-08 |
Sept.-08 |
100% |
Bid opening was held on July 15 and the contract will be awarded
at the Village Board Meeting on July 24. |
|
Tower 3 Repainting |
This work consists of making minor repairs and priming and
repainting the interior and exterior of the water tower. |
Sept.-08 |
Dec.-08 |
95% |
Bid openig was held on June 20 and the contract will be awarded
at the Village Board Meeting on July 24. |
|
Well 1, 2 & 5 Demolition |
This work consists of abandonig the wells and demolitioning the
buildings at each site. |
Sept.-08 |
Dec.-08 |
95% |
Engineers are in the process of finalizing to scope of work.
Prep work is being done on the well houses this month before
demolition. |
|
Projects Currently Underway |
Description |
Est Start |
Est Finish |
% Comp |
Current Status |
|
2008 MFT General Maintenance Program |
This Annual program continues the maintenance of existing
Village streets. The project will consist of grinding existing
asphalt surface and then placement of new asphalt, select
concrete curb and drive aprons along the following roadways:
Upper Blackhawk Dr, Patton Ave, Decatur Ave, Lee St, W. Oak St,
Pershing Ave, Grant Ave, Clark Ave, Anderson Dr, Blackberry Ct,
Spring Lake Ct, White Pine Ct, White Pine Circle, Astor Ct,
Elderberry Ct, Mayberry Ct, Wisteria Ct and Spring Lake Dr. |
Summer- 08 |
Sept.-08 |
0% |
The contract was awarded to Curran Contracting. |
|
2008 Water Main Improvements Program |
This annual program continues the maintenance and replacement of
existing undersized and/or failing main. The project will
consist of placing 8" watermain along the following roadways:
Hilltop Dr, Clayton Marsh, Washington St, Monroe St, Adams St,
Jefferson St, Elm St and Spruce St. |
Spring-08 |
Nov.-08 |
0% |
The contract was awarded to Apollo Trenchless. The
pre-construction meeting was held June 4. Letters were mailed
to residents in the area of the project last week. The
contractor will be starting work in July. |
|
Cheswick Park |
Installation of a new park at the corner of Albrecht Rd and
Gladstone. This park will consist of new playground equipment,
pavillion, benches and tables, walking path and various
plantings throughout the park. |
May-08 |
Jul-08 |
65% |
Contract was awarded to Copenhaver Construction. The contractor
is on-site and has started work. All concrete work is
complete. The asphalt path is installed and the trees have been
planted. The contractor is waiting on the delivery of the
playground equipment. |
|
Recent Projects Completed |
Description |
Est Start |
Est Finish |
% Comp |
Current Status |
|
Bordeaux Bike Path Removal |
This project consists of removing the bike path behind the homes
along the southside of Bordeaux. |
Apr-08 |
Apr-08 |
100% |
Complete |