04-26-2024
This past week was the kickoff off of our build. Land clearing and excavation has started! Next week, community members can expect more of the same; land clearing and moving dirt from the build site.
Click HERE for today's updated photos.
04-19-2024
Today we officially broke ground! We cannot thank everyone enough for all of the support for this project. Next week, residents and community members can expect to start to see construction activity and the beginning of the project to start with the moving of land an excavation.
Click HERE for today's groundbreaking photos.
04-12-2024
We have groundbreaking news! On Friday, April 19th 2024 at 4:00 P.M. we will have our official groundbreaking ceremony for our new police facility.
The new police department will be built near the current Village Hall (600 Harvest Gate Drive) with a forthcoming address in the 2600 block of Village Hall Drive.
The police department anticipates some commercial truck activity in the area this coming week nearing the groundbreaking date. The project will start with site clearing and grading.
We would like our community to be well informed of the construction plan and phases as construction may temporarily cause additional truck traffic, noise, or dust during building.
To better assist community members, we encourage individuals to follow us on social media for updates. Community members may also visit our website at https://bit.ly/PDBuild for construction updates.
Lastly, the community may sign up for Nixle Emergency Text Messaging. Community update messages may be sent out as necessary for those Nixle subscribers who are signed up to receive non-emergency messages.
We sincerely appreciate the patience and understanding of our residents, businesses and community during this project. We are extremely excited for this huge milestone for the Village and are looking forward to sharing its progress along the way!
05-31-2024
This past week community members were able to see crews begin to set up the construction site fencing around the property, continue working on site grading, working on adding site utilities, excavating and preparing for concrete to start in the next several weeks.
Click HERE for today's updated photos.
05-24-2024
This past week community members watched as crews continued excavation and land clearing, began adding site utilities and started ground leveling.
Next week, community members can expect a continuation of the same; land clearing, moving dirt from the build site, utilities, digging, leveling and site preparation.
Click HERE for today's updated photos.
05-17-2024
This past week the crew continued excavation and land clearing and started preparation for site utilities.
Next week, community members can expect more of the same; land clearing, moving dirt from the build site and adding site utilities.
Click HERE for today's updated photos.
05-10-2024
This past week the crew continued more excavation and land clearing. It is already starting to take on some shape.
Next week, community members can expect more of the same; land clearing and moving dirt from the build site and preparation for site utilities.
Click HERE for today's updated photos.
05-03-2024
This past week the crew continued excavation and land clearing. Due care was taken to preserve the existing bricks as they were moved by the team to ensure they will be transferred safely to the new location of the Veterans Memorial upon conclusion of the construction. The memorial will be refreshed and relocated on the property, closer to the roadway, which should provide additional visibility for passers-by.
After the relocation, the Veterans Memorial will remain accessible as a commemorative gathering space to honor those who served.
Next week, community members can expect more of the same; land clearing and moving dirt from the build site.
Click HERE for today's updated photos.
06-28-2024
The site really took on some changes this week. Mother Nature has made things interesting for our crews but they are doing a great job working around the rain and continuing to make progress. Concrete is on its way!
Click HERE for today's updated photos.
06-21-2024
Crews are really moving along getting things ready for concrete. The site has taken addition shape and depth, site utilities are getting in place and crews are preparing for concrete. These foundational steps will take awhile but are crucial. And we are very thankful to the crews out there for the awesome job they are doing.
Click HERE for today's updated photos.
06-14-2024
It is looking great out there! This past week was all about the digging. In the coming weeks the community can expect to see more moving of land, site utilities and preparation for concrete!
Click HERE for today's updated photos.
06-07-2024
Today marks the end of seven weeks after we broke ground! And things are certainly looking different out there. The full construction fence is up and the site is taking shape. This past week was more land clearing, and really getting down into the earth. In the coming weeks the community can expect to see more moving of land, site utilities and preparation for concrete!
Click HERE for today's updated photos.
07-19-2024 and 07-26-2024
The foundation is beginning to be formed with more concrete. This will be a long process over the next few weeks.
Click HERE for photos.
07-12-2024
Concrete will be starting! Community members will be seeing the site take take on some shape here in the upcoming months.
Click HERE for photos.
07-05-2024
Mother Nature kept at it again this past week with more rain. But our crews worked around it and continued doing great things at the site. Crews are getting it prepped for concrete, which is coming here soon - as long we can get our weather to cooperate.
Click HERE for today's updated photos.
08-30-2024
Walls and structure will be the name of the game for the foreseeable future as we move into September. We cannot wait to see how things begin to move from the ground up. Literally!
Click HERE for today's updated photos.
08-23-2024
Click HERE for today's updated photos.
08-16-2024
Foundation work continues and the walls are getting taller and forming. Sitework continues to occur. The community will see the site continue to take shape and a more solid form.
Click HERE for today's updated photos.
08-09-2024
As the foundation is going in around the site, the formation of walls are appearing and sitework continues to occur. The community will see the site continue to take shape and a more solid form.
Click HERE for today's updated photos.
09-27-2024
09-20-2024
Twenty-two weeks ago we broke ground on a grass field. Now, our new future police department is laid out and we can see where individual rooms, halls, etc. will be Creating more structure is on the forefront. These crews are doing great work and we are grateful for each member making this building a reality for us.
Click HERE for today's updated photos.
09-13-2024
Drainage is also key for this site. Crews have worked on drainage for the current project and for the completion and future.
Click HERE for today's updated photos.
09-06-2024
Walls are getting taller and more structure work. It's all about a strong foundation.
Click HERE for today's updated photos.
10-25-2024
Walls are still being worked on and it has been amazing watching the masons work. We now have full story masonry in place to both the south and west part of the building. Every day we are getting closer and closer to our new PD!
Click HERE for today's updated photos.
10-18-2024
It's all about the walls and structure. These masons are really helping to show us what this building is going to be. We cannot wait!
Click HERE for today's updated photos.
10-11-2024
Click HERE for today's updated photos.
10-04-2024
We have beams!! And look how much the structure has grown. Things are going to start really changing as the metal framing and beams are added. We are excited to see next week's additions.
Click HERE for today's updated photos.
11-29-2024
Happy Thanksgiving Lake in the Hills!!!
Click HERE for today's updated photos.
11-22-2024
Crews will continue on working exterior walls on first and second floor levels and structural work.
Click HERE for today's updated photos.
11-15-2024
We are nearly a quarter of the way complete!! Scaffolding is up at the second floor level as crews work on the exterior walls. Large structural beams are in and concrete work continues.
Click HERE for today's updated photos.
11-08-2024
Concrete has started! We have floors forming in the new PD.
Click HERE for today's updated photos.
11-01-2024
Click HERE for today's updated photos.
12-20-2024
Today's update comes with some snow and some cool inside and up close pictures, courtesy of our incredible building commissioner. Even with this cold and snowy weather, our construction crews carry on. We are so grateful for them working out there in these frosty conditions. They are doing an amazing job.
We will have only one more update in 2024 and cannot wait to compare how far we have come since April and throughout the last eight months.
Click HERE for today's updated photos.
12-13-2024
Click HERE for today's updated photos.
12-06-2024
We are in the countdown for the final weeks of 2024 with 3 weeks left. We are just in awe of how much the building is changing weekly. Keep checking back in with us for the last of this year's progress!
Click HERE for today's updated photos.
01-31-2025
01-24-2025
Here is something we do not get to see every day... the beams being added to the new PD! It has been incredible to watch what our crews accomplish each week, even in the temperatures and with the snow we've gotten.
Click HERE for today's updated photos.
01-10-2025
We are at 38 weeks of construction. It is cold, it is windy...but our amazing construction crew is still out there taking care of business.
Click HERE for today's updated photos.
01-03-2025
Happy New Year Lake in the Hills! We are 37 weeks in from the day we broke ground and the weekly changes never ceases to amaze us. We are excited to continue to watch the building form and change over the next year and to share it with our community.
Click HERE for today's updated photos.
02-21-2025
The temperatures were bitterly cold this past week, affecting everyone in the community. We are grateful for the continued work and efforts of our crews who are out there daily. Thank you!
Click HERE for today's updated photos.
02-14-2025
02-07-2025
Chief Mannino took some cool photos to share with everyone from a side of the new PD that we do not get to see very often. This view is looking from the COSTCO area towards the Residences and the backside of Village Hall. Thank you for getting this side of the project to share with us, Chief!